Modi Jalvidyut Company Limited
Upper Modi ‘A’ Hydroelectric Project — 42 MW

Project Overview
The Upper Modi ‘A’ Hydroelectric Project (UMAHEP) is a 42 MW run-of-river hydropower project located on the Modi River in Annapurna Rural Municipality, Kaski District, Gandaki Province. It forms the upper stage of the Modi Cascade Project being developed by Modi Jalvidyut Company Limited.
The project utilizes a design discharge of 17.4 m³/s and a gross head of 286.8 m to generate an estimated 243.587 GWh of electricity annually. Water diverted from the Modi River is conveyed through the project’s headworks, desanding facilities and approximately 6 km headrace tunnel to the powerhouse, where two 21 MW vertical-axis Pelton generating units are proposed. The tailrace discharge is subsequently conveyed to the Upper Modi Hydroelectric Project, forming the lower stage of the cascade.
Key Project Features
Headworks & Water Conveyance
- Diversion Weir
- 6 m high × 30 m long concrete diversion weir with overflow spillways
- Intake
- Four side intakes, each 3 m wide × 3 m high
- Desanding Basins
- Two surface desanders, each 90 m long × 10 m wide × 9.2 m high
- Headrace Tunnel
- 6,001.64 m long; finished section 3.8 m × 3.5 m
- Adit Tunnels
- Adit-1 — 130.00 m; Adit-2B — 169.88 m
Surge & Powerhouse System
- Surge Tank
- Restricted-orifice type; 10 m diameter × 43.6 m high
- Powerhouse
- Surface/semi-surface; 36 m long × 15 m wide × 28.3 m high
- Generating Units
- 2 × 21 MW vertical-axis Pelton turbines
Power Evacuation
- Transmission Voltage
- 132 kV
- Transmission Arrangement
- 11.5 km single-circuit transmission line to New Modi Substation
Contract & Implementation
- Developer / Employer
- Modi Jalvidyut Company Limited
- Contract Package
- Lot 1 — Civil and Hydromechanical Works
- Contract Model
- Engineering, Procurement and Construction (EPC)
- EPC Contractor
- SSCE–High Himalaya JV
- Design Review & Construction Supervision
- NEA Engineering Company Limited